As you well know, the goal of PMS is maximum
operational efficiency of all equipments and the
reduction of equipment downtime, maintenance
manhours, and maintenance costs. Even though the
PMS provides methods and resources to accomplish
each goal, it is not self-sufficient and does not replace
the initiative of maintenance supervisors nor reduce the
need for technically competent personnel. Recording
and feedback of maintenance and personnel data allow
continuing management analysis and improvement of
maintenance methods and personnel use. If the ships
force accepts the PMS program and makes full use of
its planning methods, the maintenance system will
promote confidence and reliability, and will be capable
of ensuring that the combat system will be available
when it is needed.
Data gathered from the fleet show conclusively that
ships that adhere to their PMS schedule maintain a
significantly higher state of materiel readiness with no
greater maintenance manpower usage than ships that do
not. The SERT concept is designed to ensure that the
combat system PMS is properly scheduled, managed,
and used.
PMS PROGRAM (COMBAT SYSTEMS)
The primary ingredients of the PMS program areas
follows:
l
l
l
l
Comprehensive procedures for planned
maintenance of the combat system, subsystems,
and equipments
System fault isolation procedures
Scheduling and control of maintenance task
performance
Description of the methods, materials, tools, and
personnel required for maintenance
Adherence to the PMS
following results:
l
l
l
l
Improved confidence
Reduced testing time
program will provide the
in system maintenance
Elimination of redundant testing resulting from
lack of coordination
Detection of most malfunctions during
scheduled maintenance events
MAINTENANCE SCHEDULING
The normal flow of events and requirements the
SERT will use in developing an integrated maintenance
schedule is illustrated in figure 4-9. This figure shows
maintenance management responsibilities and the
sequence of events that flows from the departmental
master and work center PMS record books (containing
the Maintenance Index Pages [MIP]), through the
scheduling tools (Cycle, Quarterly, and Weekly
Schedules), to test actions, unscheduled (corrective)
maintenance, and reporting. The figure does not show
the variants and constraints the SERT must consider in
the quarterly, weekly, and daily scheduling due to the
shipboard environment. These considerations were
discussed earlier in this chapter in the description of
SERT.
Maintenance Index Page (MIP)
The MIP contains a brief description of the
requirements on the maintenance requirement card for
each item of equipment, including the periodicity code,
the manhours involved, the minimum required skill
level, and (if applicable) the related maintenance
requirements. The MIPs for all equipments in a
department are contained in the department master PMS
record. The department master PMS record is used by
the department head to schedule maintenance on the
PMS schedule forms. Each work center has a PMS
record that contains the MIPs that apply to that work
center.
Cycle Schedule
The Cycle Schedule is used by the combat system
officer (CSO) to plan quarterly, monthly, and other
requirements. It is a visual display of preventive
maintenance requirements based on the ships overhaul
cycle.
Quarterly Schedule
The Quarterly Schedule, planned from the Cycle
Schedule, is a visual display of the ships employment
schedule. This schedule is prepared by the CSO in
cooperation with division officers, maintenance group
supervisors, the system testing officer, and SERT
members, and shows the current status of preventive
maintenance for each group. The Quarterly Schedule
assigns specific requirements in conjunction with the
ships operational schedule.